Dabur India Ltd. was one of our most ambitious and starting career projects between 1996-2003 where we job three Installations in different sites. It was counted as part of our 30 Years Excellence as HVAC Company finest work. Now here's a Brief Case Study of the Central AC System for Commercial for Dabur India Ltd. with the whole process and detailed overview of quantity.




Dabur India Ltd. Project Challenges and Solutions

  1. When we signed a project deal for Heating & Ventilation Air Conditioning with Corporate Company Dabur Ltd. it was a Centralized Air Conditioning System Implementation in Dabur Corp office whose Total TR ( Ton of Refrigeration ) Counted as 196 TR and this job started in mid of 1996 were we total setup central ac and pack-up Centralized AC Installation within a year.

  2. After this excellent first attempt we took other three big Installation jobs for dabur whose total TR Volume crossed 1500+ TR including HVAC Works like Centralized Air Conditioning High Slide Chiller Implementation Service. You can saw the project details below:


Central Air Conditioning System for Dabur Head Office

One of Head offices of Dabur India Ltd. situated in Sahibabad, Uttar Pradesh where we work for Air Conditioning by Central Module and Install High Slide Chillers. Here System regulates the chilled air and conveys a comfortable atmosphere for employees and all kinds of staff.


High Slide Chillers for Dabur Pharma

For Pharma suitable for Dabur, Chillers Installation held in the amount of 3X40TR whereby ducts system control the warm and chilled air as per the season and present human percentage in zones of Building.


Gallery of Dabur India Ltd. HVAC Work Project


Conclusion

HVAC journey with Dabur India ltd. is one of the milestones in the history of our company and entails starting of an epoch of multi-variable and large-volume centralized air conditioning systems. This project demonstrated our technical knowledge skills, our project management ability and our client satisfaction results as we installed our first 196 TR in 1996 and since then have implemented the completion of more than 1500+ TR and at various sites. All stages, including the installation of the corporate offices to the pharmaceutical-grade HVAC systems, demonstrated our capacity to supply efficient, scalable and season-adaptive systems. Dabur India Ltd. was not only a client; it was a stepping stone that aided us to achieve our 30 years of HVAC excellence.